The Ongoing Issue with the Capital's Scaffolding-Clad Hotel?

Scaffolding surrounding a hotel on a busy street
The protective structure enveloping the hotel on a central thoroughfare may not be entirely dismantled until 2027.

Along the most frequented avenues in the heart of Scotland's historic capital sits a monolith of construction framework.

For five years, Radisson's G&V Hotel on the intersection of a key historic street and George IV Bridge has been a plastic-wrapped eyesore.

Tourists are unable to reserve stays, foot traffic are funneled through narrow walkways, and establishments have left the building.

Repair work began in 2020 and was initially projected to last a few months, but now exasperated residents have been told the scaffolding could persist until 2027.

Extended Timelines

The main contractor, the primary firm, says it will be "close to the conclusion" of 2026 before the first sections of the frame can be taken down.

A local authority figure a city representative has called it a "eyesore" on the area, while preservation advocates say the work is "extremely disruptive".

What is transpiring with this seemingly endless project?

A clean, modern hotel facade without scaffolding
Scaffold-free - how the hotel looks in its intended state on the company's website.

Background Issues

The 136-bedroom hotel was developed on the site of the old local government offices in 2009.

Projections from when it originally launched under the Missoni Hotel banner, put the cost of construction at about thirty million pounds.

Remedial efforts started shortly after the start of the Covid pandemic with the hotel itself shut for business since 2022.

Part of the road and a significant portion of sidewalk leading up to the junction of the tourist drag have been left out of action by the work.

Walkers going to and from the an adjacent district and Victoria Terrace have been compelled single-file into a confined, sheltered corridor.

A dining establishment Ondine quit the building and moved to a different location in 2024.

In a release, its management said building work had obliged them to modify the restaurant's appearance, adding that "guests were entitled to a superior experience".

It is also hosts dining franchise a pizza restaurant – which has hung large signs on the structure to inform customers it is still open.

The hotel under construction in 2008 Scaffolding going up on the hotel in 2020
Pictures show the the building under construction in September 2008 (left) and the work beginning in 2020 (right).

Missed Deadlines

An communication to the a city committee in January this year suggested that the process of "uncovering" the exterior would start in February, with a total takedown by the end of the year.

But the contractor has said that is incorrect, pointing to "highly complicated" construction issues for the postponement.

"We project starting to take down parts of the framework towards the end of the coming year, with additional work continuing thereafter," the company commented.

"Efforts are underway closely with all parties to ensure we deliver an better site for the community."

Local and Conservation Frustration

A conservation official, lead of heritage body the Cockburn Association, said the work had added to the city's reputation of being "leisurely" for development.

She said those involved in the project had a "obligation to the public" to reduce disruption and should blend the work into the city's design.

She said: "It causes the walking experience in that section really difficult.

"It is perplexing why there is not some attempt to incorporate it within the street view or create something more aesthetic and cutting-edge."

People walking through a narrow, covered walkway next to scaffolding
Tourists have been obliged to walk down a narrow covered walkway on the affected thoroughfare.

Project Response

A project spokesperson said work on "measures to aesthetically improve the site" was ongoing.

They stated: "We understand the annoyances felt by nearby inhabitants and shops.

"This constitutes a lengthy and protracted process, demonstrating the difficulty and scale of the remedial work required, however we are focused on concluding this necessary work as soon as is feasible."

The council leader said the council would "continue to put pressure" on those accountable to finish the project.

She said: "This framework has been a problem for years, and I share the annoyance of inhabitants and local businesses over these persistent hold-ups.

"That said, I also acknowledge that the contractor has a obligation to make the building structurally sound and that this restoration has been hugely complex."

Kelly Doyle
Kelly Doyle

A passionate life coach and writer dedicated to helping others achieve their dreams through actionable advice and motivational content.